SOLAR PANEL PROJECT

An installation of a 10K solar panel system on the Micro Fit program has recently been installed at Sydenham Street United Church, Brantford, Ontario.

 

Our system consists of 52 solar panels rated at 220 watts each and 52 enphase micro inverters rated at 190 watts each.

 

This system was installed on an approximately 45° sloped roof facing a southerly direction and was completed on August 6, 2010.

 

System cost was approximately $75,000 with a private donation of $50,000 given to the church leaving a church obligation of $25,000.

 

The feed in tariff program of .802 cents per kilowatt/hour is guaranteed for 20 years.

 

Our forecasted income for 20 years is $205,900 broken down as follows:

Year       1                              $11,373                 Year       11                           $10,285

                2                                11,259                                                 12                             10,182

                3                                11,146                                                 13                             10,081

                4                                11,035                                                 14                               9,980

                5                                10,925                                                 15                               9,880

                6                                10,815                                                 16                               9,781

                7                                10,707                                                 17                               9,683

                8                                10,600                                                 18                               9,586

                9                                10,494                                                 19                               9,491

                10                             10,389                                                 20                              9,396

 

It is recommended that any organization considering this type of program consider the following steps.

1.            Pick a reputable contractor

2.            Apply to Ontario Power Authority (OPA) for approval of project.

3.            Do nothing until written authority is received from OPA.

4.            Contact your local power authority for input and advice.

5.            Obtain structural engineering report approving the building for installation.

6.            Meet with ESA and receive their approval.

7.            Obtain building permit.

8.            Meet with contractor, ESA and local electrical authority for agreement on installation location and all      procedures.

9.            After completion and hook up to the grid forward to OPA necessary documentation for contract approval.

10.          Receive contract in writing from OPA.

11.          Payment will commence at a date following this contract being received by the municipality (The City of                 Brantford payments are monthly).

 

Please note: A reputable contractor will do most of the above items on your behalf if negotiated as part of the contract in advance.

 